Technical project details¶
Original Brief¶
Functionnal specifications¶
Technical specifications¶
Planning¶
date | iteration | comment |
01-06-2001 | specifications | ops team & project owner |
22-06-2001 | snapshot validation | ergonomy validation |
13-07-2001 | test pilot version | 1st release on test instance |
15-07-2001 | user feedback | |
17-09-2001 | test pilot version | 2nd release on test instance |
19-09-2001 | ETF meeting | |
26-09-2001 | prod pilot version | 1nd release on prod instance |
31-10-2001 | start CSIRT campain | |
31-10-2001 | start CSIRT campain | |
10-11-2001 | campain feedback | |
24-11-2001 | EVO meeting | |
december | prod pilot version depending on CSIRT priorities | 2nd release on prod instance |
january | final prod pilot version | 3nd release on prod instance |
march 2012 | final prod version |